Kenley Inc.
Friday, December 17, 2010
R&F Remodel
The project is complete, on schedule and on budget. the challenge was that the time alotted for this project was 30 days, fifteen days for construction and fifteen days for the equipment install. follow this link to view more photos of the entire process. http://picasaweb.google.com/kenleyinc/WMHRFRemodel#
Monday, December 6, 2010
R&F Remodel
Walls are painted, flooring is installed, cabinets are installed, and the new X-Ray equipment install is underway.
Friday, November 19, 2010
Thursday, November 18, 2010
R&F Remodel (Weiser Hospital)
Wednesday, November 10, 2010
R&F Remodel (Weiser Hospital)
It has been one week since we started this project and so far everything is going to schedule.
The walls are all framed up and the plumbing, electrical, and venting are all roughed in.
Friday, November 5, 2010
R&F Remodel (Weiser Hospital)
Abatement Pro has started the structural demolition and TurnKey Medical has started on the existing X-Ray equipment demolition.
Sunday, October 10, 2010
R&F Remodel (Weiser Hospital)
We will start this project November 5th, 2010 and and hope to have it completed by December 17th 2010.
TurnKey Medical out of Boise ID will be replacing the X-Ray equipment, and we will be doing the structural design and construction to support the new equipment. Also we will take this opportunity to turn the old darkroom and the computer room into new workstations. Budget permitting we will be updating all the finishes in the X-Ray area as well.